An issue note shows what left the store. A reconciled job record explains what entered the product, what came back and what still needs attention.
Follow material from stores through production and the return check.
A workshop sends 120 kg of steel to a fabrication job. By evening, some steel is in the finished work, some is in the offcut bin and some has come back to the store. A few bars are still beside the workbench. If the job sheet simply says “120 kg used,” the record hides what actually happened.
Tracking materials issued and returned gives the owner a clearer answer: where did the material go, and what still needs attention? It also helps the storekeeper avoid buying replacements for usable stock that has never been recorded as returned.
Here is a practical routine for a small fabrication workshop in Nepal. The quantities, dates and NPR values below are hypothetical. They illustrate physical control and planning, not Nepal accounting or tax treatment.
Separate movement from consumption
Sending material from the store to the production floor changes its location. It does not, by itself, tell you how much has entered the product.
Keep separate records for material issued, additional issues, usable returns, material incorporated into output, process scrap and material still on the floor. A work-in-progress location, often called WIP, can help show material awaiting the next production step.
ERPNext’s Work Order documentation provides an implementation example: it describes transferring materials to WIP and returning unused components to stores. This is a useful reference pattern; your workshop can begin with controlled paper forms or a spreadsheet.
Illustrative stock check before material is issued to a production job.
Give every movement a job and a unit
Before the first issue, agree the job reference, item code, measuring unit, source and destination. Record the person handing over the material and the person receiving it.
For steel tracked in kilograms, do not quietly enter “three bars” as though that were three kilograms. Record both measures if useful, with an agreed conversion or actual weighing method. Separate grades and sizes even when they look similar.
Use a simple movement register:
| Field |
Example entry |
| Job reference |
FAB-026, a hypothetical fabrication job |
| Item and unit |
Steel section S-01, kg |
| Movement |
Issue, usable return or approved correction |
| Quantity and locations |
120 kg, Store A to production area |
| Evidence |
Date, movement reference, sender and receiver |
| Condition on return |
Usable, inspection required or scrap |
Retain the original movement reference when correcting a mistake. A second entry with the same information should not become another physical issue. In a spreadsheet, check reference numbers before adding rows; in planned software, ask for duplicate-reference validation and a traceable correction process.
Link each movement to the job while retaining its own reference and evidence.
Reconcile the job before deciding what it cost
Consider one steel item on one hypothetical job, with no opening floor balance and no additional issues. At the review point, the 120 kg issued is accounted for as follows:
| Disposition at review |
Quantity |
Planning value at NPR 200 per kg |
| Incorporated into output |
90 kg |
NPR 18,000 |
| Process scrap, separately identified |
5 kg |
NPR 1,000 |
| Usable material returned to stores |
20 kg |
NPR 4,000 |
| Material still on the floor for this job |
5 kg |
NPR 1,000 |
| Total accounted for |
120 kg |
NPR 24,000 |
120 kg issued = 90 kg incorporated + 5 kg scrap + 20 kg returned + 5 kg remaining
The 90 kg excludes the 5 kg scrap. Neither returned material nor the remaining floor balance is also counted as incorporated material. The NPR column applies one assumed rate solely to make the quantities easier to discuss; it is not a journal, selling price or complete production cost.
Do not conclude that the job’s finished output cost NPR 24,000. Labour, overheads, valuation methods and the treatment of scrap require a separate costing policy. Have the accounts team review that policy with the appropriate adviser before connecting stock movements to ledger postings.
Hypothetical quantity reconciliation with each kilogram counted once.
Separate usable material and offcuts before recording a return.
Inspect returns before making them available
A return needs a quantity and a condition decision. Full usable material can follow your normal receiving check. A short offcut may still have value but may need its own size description or storage location. Damaged material should not appear available for the next job just because it has arrived at the store.
Keep reusable offcuts separate from process scrap. Record what was returned against the original job, and confirm that the store actually received it. A production note saying “returned” and an unchecked pile beside the door are different things.
If scrap is later sold or reused, link that later action to its record. Its existence in the example is not evidence of a recoverable value or an automatic reduction in production cost.
Inspect condition before making returned stock available.
Check what automatic consumption assumes
Some systems propose consumption from a bill of materials; others can use transferred quantities. ERPNext’s Material Consumption documentation describes both bases and multiple consumption entries against a work order.
The practical question for a manager is whether the proposed quantity matches what happened. A transfer of 120 kg should not silently settle a record showing usable returns and material still on the floor.
When evaluating a workflow, ask the team to demonstrate a partial job, an extra issue, a return and a correction. Confirm how earlier consumption entries are considered when finishing the job, so the same material is not recorded twice.
Close the gaps before closing the job
Our example still has 5 kg on the floor. Give that balance an owner: use it in further production, return it after inspection or investigate a count difference. Do not clear it with an unexplained adjustment merely to make the job look complete.
Connect the review to the teams that need it. Inventory confirms stock and condition. Production confirms actual use. Task Management assigns unresolved checks. CRM can carry an approved delivery update, while Accounts reviews valuation and proposed postings. HRM may supply authorised labour information if a future costing workflow needs it.
These are connections to evaluate for planned WorkSphere workflows, not claims that specific integrations are live.
A checklist for your next material movement
Before signing an issue or return, confirm:
- The job, item code and measuring unit match the record.
- The quantity was counted or measured using the agreed method.
- Source, destination and condition are recorded.
- The receiver accepts the quantity and the movement reference is unique.
- Any difference has an owner and a review date.
At job review, reconcile all movements with output, scrap and the remaining physical balance. Keep the supporting notes with the same job reference.
Resolve the physical balance with evidence before closing the exception.